Fibrecut between Arnhem and Eindhoven
We have a cable cut between Arnhem and Eindhoven.
Our contractor is on site, and they are busy with restoring the cables/fibers.
We do not have a clear ETR yet, but we expect in the (late) afternoon today.
Updates
Sorted by — Most recent
- Resolved4/19/202217:31
Fibrecut between Arnhem and Eindhoven
The repairs have finished. If you still have issues, please do not hesitate to contact the Eurofiber NMC - nmc@eurofiber.com
- Resolved4/19/202215:52
Fibrecut between Arnhem and Eindhoven
Our contractor informed us that the ETR has been moved to 19:00 CET
Currently the ETR is set at 19:00 CET.
- Resolved4/19/202214:10
Fibrecut between Arnhem and Eindhoven
Our contractor is still busy splicing, but we can see many links restoring allready.
The ETR remains the same at 18:00 CET.
- Resolved4/19/202212:30
Fibrecut between Arnhem and Eindhoven
Our contractor informed us, that the splicing of the fibers has begun, and that the first few links should start restoring soon.
Currently the ETR is still 18:00 CET.
- Resolved4/19/202209:10
Fibrecut between Arnhem and Eindhoven.
We asked our contractor, if they were able to provide an ETR yet.
They told us that they expect the problem to be solved in the late afternoon.
It could take untill 18:00 CET.